LYF Collingwood
Client: Furn-niche
Type: New Build
Keys: 105 + Common Areas
Program: 30 days (in total)
Location: Collingwood, Melbourne
Date: 2023
Type: New Build
Keys: 105 + Common Areas
Program: 30 days (in total)
Location: Collingwood, Melbourne
Date: 2023
Scope of Work:
- Installation of joinery, mirrors, TV mounts, various hooks, and wall cabinets.
- Assisting Furn-niche in meeting their PC requirements.
- Decommissioning rooms to support late-stage design changes.
- Warehousing and auditing remaining stock for use in revised design plans.
- Defect rectification and on-site maintenance of joinery.
Challenges:
- 20 rooms underwent significant design changes during the final phase of the project.
Solutions:
We worked closely with Furn-niche, Urban, and LYF to develop methods and solutions that accommodated the new design using existing goods. This ensured work was completed within the original timeline and allowed us to provide ongoing maintenance support during hotel operating hours.